LOCATION: Monterey, CA (2017)
As the prime contractor, Ironwood Commercial Builders, Inc. completed the renovation of Building 836. The project scope of work included site protection/restoration, scaffolding, demolition, mold remediation, roofing, architectural metals, exterior insulation and finish system (EIFS), framing /drywall, painting, plumbing and electrical. IBCI self-performed the replacement of failing exterior stucco on Building 836 with a new EIFS system. ICBI oversaw multiple subcontractors performing various trades and performed contract administration requirements that included P6 scheduling, quality control and site safety and health. ICBI worked with the EIFS manufacturer (PAREX) and the Army Corps of Engineers to deliver an alternative value-engineering solution to the traditional stucco system originally specified.